Tiernan & Patrylo was tasked with redesigning the south side of Bekaert’s manufacturing plant. The revitalization project was $8.5M and consisted of moving or installing 196 pieces or production equipment and all necessary structures, pits, trenches, electrical and mechanical provisions. While working on the revitalization project, the existing plant caught fire on the north side of the building.

Tiernan & Patrylo worked around the clock to design and implement all new plant utilities near the fire damaged areas to have the plant up and running again in 15 days. Bekaert then hired Tiernan & Patrylo with confidence to redesign the fire damaged areas.